Recently, our company has made one new breakthrough after another in high-pressure water jet cleaning construction, challenging heights time and time again, winning reputation for the company in front of customers, truly fulfilling the company's commitment to continuously strive for the rapid development of society and local economy, and truly realizing the company's established social commitment of doing every project, setting a flag, making friends, and showing love.
On the basis of receiving high recognition from Party A for the condenser of the 1000MW unit of Xinhai Power in Lianyungang and being featured in Party A's newspaper headlines, and receiving recognition from Party A for the condenser acid washing of Baosteel Energy saving and Environmental Protection Technology Co., Ltd. in Shanghai, under the leadership of Zhang Heng, the construction manager of our company's engineering center, we have achieved good results in the chemical high-pressure water cleaning of Unit 1 and Unit 2 in the air cooling island of Wutian Coal and Electricity Metallurgical Co., Ltd. in Fugu, Shaanxi. This has made a significant breakthrough for our company in the chemical high-pressure water construction of the air cooling island and has milestone significance.
The engineering dispatch order for this project was issued by the marketing department on August 5th, 2017, requiring personnel and equipment to enter the site on August 8th. Upon receiving the dispatch order, the engineering center attached great importance to it and immediately conducted research on this project, determining the construction and scheduling plan
Due to the fact that the high-pressure jet for air cooling in this project is a thorough flushing after the dissolution of chemical agents, it is required that the high-pressure water jet must be a high flow equipment. According to the company's equipment dynamic management screen, the air cooling island of Inner Mongolia North United Power Mengxi Power Generation Co., Ltd. has just been constructed and accepted. The construction equipment for this project is 230L/min, 132KW high-pressure jet equipment, which meets the construction needs of this project. The engineering center immediately dispatched Mengxi construction manager Ma Haisheng to ship the equipment to Wutian Coal and Electricity Metallurgy Co., Ltd. in Fugu, Shaanxi. At the same time, some construction personnel for this project were transferred to Fugu, Shaanxi along with the equipment, and cooperated with the Shaanxi regional manager to coordinate the pre construction work.
Arrange the Technical Service Department of the Engineering Center to produce 4 tons of specialized cleaning agents for air-cooled islands using a formula.
The Technical Department of the Engineering Center has developed a plan to improve the design of the air cooling island chemical atomizer and notified the Equipment Support Department to immediately make improvements based on the drawings. After the improvements are completed, effect tests will be conducted immediately.
4. Appoint Zhang Heng as the construction manager for Unit 1 and Unit 2 of Shaanxi Fugu Wutian Coal and Electricity Metallurgy Co., Ltd. The project will be immediately staffed and construction preparations will begin on the same day.
The personnel and equipment of the project arrived at the site on August 9th. Due to the long-term operation of the air cooling island, it was not cleaned in a timely manner, covered with dust, and the condensation effect was severely reduced, resulting in a continuous decrease in load. The party A requested us to expedite the construction. Thinking what customers think and being urgent about their needs has always been our company's customer philosophy. Without hesitation, Zhang Heng immediately organized all construction personnel to carry out tense and orderly construction.
For the benefit of our clients, our construction personnel were divided into black and white shifts under the leadership of Zhang Heng, taking turns cleaning 24 hours a day without stopping. Finally, on August 19, 2017, the project was completed and successfully passed the acceptance of Party A. The acceptance result showed that the surface penetration rate was 95%, the surface of the tube bundle showed a metallic luster, and the chemical cleaning did not damage any equipment.
After the inspection, the exhausted workers showed a caring smile, and being recognized by Party A is the greatest reward for our efforts. The marketing model of Sciengreen's word-of-mouth promotion has always been carried out, with the saying 'Gold and silver cups are not as good as customer reputation, and gold and silver awards are not as good as customer praise'.